15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

over the past 15 years a business owner has made at most $4,000 in profit each week​
Which side effects can be caused by LSD usage? (multiple answer) hallucinations heart failure death decreased blood pressure
What is the equation in point slope form of the line that passes through the point (−2, 4) and has a slope of 5? Drag and drop the appropriate number, symbol,
In the figure below, CD bisects
The measures of the angles of a triangle are 37 degrees, 53 degrees, and 90 degrees. Classify the triangle A. Right B. Acute C. Equiangular D. Obtuse
I need help I don’t understand algebra
please help 50 points for this one question! in a midsummer night’s dream who is the most selfish person and why? Oberon Helena Demetrius
20 points What is the objective of a company’s internal control? The objective of a company’s internal control is to provide reasonable ________ that its financ
Rewrite the product (x-3)^2 in standard form. Show your work
I need help on the Math question?