15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

If item costs $99.99 with 15% off and I get final price. It then asks me what percentage of savings. How do I get the percentage of savings
next term in sequence 61, 122, 244, 488
What is 38/50 as a decimal... and what is 28/50 as a decimal? PLEASE HELP ME !!!! i hate struggling with homework!
What is 9x^2-24x+ 16
how do you now 11/33 is a simplest form
If item costs $99.99 with 15% off and I get final price. It then asks me what percentage of savings. How do I get the percentage of savings
2 friends want to equally share 4/3 feet of rope.What length of rope should ea friend get?
How do you say I was born in the Philippines in Spanish
HOW TO FIND THE MISSING NUMERATOR IN ANY FRACTIONS LIKE 4/8=  ?/4
What is 60 divided by 100 and why? ( I got 0.6 but I'm not sure ) plz hurry